LPG INSTALLATION
Mobil Napier Street, Whitehall
FEBRUARY 2021
EQUIPMENT USED
-Tipper x 5
-Tipper & dog
- Nitrogen truck
- 20 tonne excavator
Services:
Installation of LPG at new Mobil Whitehills.
Organise transport and installation of 2 x 50KL
Coordinating the tank hole being excavated
Removal of 2000cbm soil
Installation and painting of pipe work
Organising sand, rock and concrete to be delivered to site
Organising water delivery